Tozzi Green repairs damage caused by installation work

by daily weby
The CEO of Tozzi Green, Davide Giachero (left), during a meeting with the beneficiaries of the compensation measure.

The Tozzi Green company is taking steps to compensate and repair direct and indirect damage caused by the construction of the Farahatsana hydroelectric power station (HPP) and its facilities. The results of the rehabilitation work carried out were presented yesterday to Mahitsy. The HPP Farahatsana power plant supplies the Antananarivo Interconnected Network via a 38 kilometer high voltage line to the Anosizato electrical substation. It draws from the Ikopa River and has a total capacity of 136 GWh. During the installation and production phases, homes and domestic infrastructure were damaged, among other things, by the frequent passage of machinery.

A prior community consultation meeting took place last year, between the president and CEO of Tozzi Green Madagascar, Davide Giachero, the authorities of the Ambohimasina Mahitsy commune and surrounding areas, and residents, following which he It was decided that the company would take charge of the rehabilitation of damaged houses and infrastructure.

The rehabilitation works consist of creating a reinforced concrete framework to stabilize the buildings, repair cracks and improve the aesthetic appearance according to the principles of the resettlement policy. Eligibility criteria and compensation methods have been developed taking into account local realities.

He is careful